|
Town
Halts Ballfield Mining Operation
By Dan
Sapir and Dennis
Randall
(MARCH
2002) Within a 72 hour
period, two cease and desist orders were issued against earth
removal operations by Zoning Enforcement Officer Paul Armstrong.
The first order was issued February 19th against the Pottle Street
ballfield project when truckloads of processed sand were spotted
being removed for private sale. The second order was issued
February 22nd against Duxbury Construction for operating without a
permit on land located at the end of the access road adjacent to
United Rentals (See related story).
The
Observer had been contacted by numerous municipal and private
sources regarding operations at the Pottle Street site. Allegedly,
materials were being removed by contractors in 18 wheel rigs.
Evidence of processing was observed in the form of a portable
screener, excavator and several stockpiles of processed sand,
tailings, subsoil and signs of recent excavation. The next day
(Tuesday, February 19), we followed fully loaded trucks from
Pottle Street to a private site in Pembroke. Based upon this
information Armstrong shut down the operation pending the results
of an investigation.
The following
morning (Wednesday, February 20), despite the stop work order, we
followed another 18 wheeler from the site all the way out to Route
495 bound for a Fairhaven jobsite. Armstrong reiterated the stop
work order. A few days later on Friday, Armstrong, for the third
time, had to stop excavating activities. The company conducting
the work was W.E. Lyons Sand & Gravel, a Plympton based
company whose owner, William "Billy" Lyons lives in
Kingston. Lyons contacted the Observer and stated he was
conducting volunteer work for the Ballfield Committee and his only
interest was in helping the kids. He stated that the two large
piles of processed sand had a value of $10,000 that he would take
as a loss if unable to remove it from the site. He asked if we
would approve the removal of the material and in exchange he would
wrap up his excavations. We advised Lyons we were not in the
permitting business and sympathized with his problem. We asked
under what authority or contract he was conducting this
excavating, processing and removal and he said there was nothing
on paper. We suggested he contact whoever authorized his presence
to commit the authorization to writing. Lyons explained he had
done some volunteer excavating work and the sand represented some
form of compensation. He declined to name the person(s) who
authorized his enterprise.
 |
| Lyons Mining Operation: Uncompacted
organic laden sub-soil replaces sand removed during
"below-elevation" mining while additional material
awaits removal. Large glacial boulder has limited excavation
right of photo. Photo/Dennis Randall |
It should be noted
that the Pembroke job site represented a private residence on
Spring Street doing a septic system repair. The contractor for the
job purchased six (6) truckloads of sand, 28 yards per truck at
$7.00 a yard -- $1,176.00 -- delivered.
Pembroke Board of
Health Regulations require washed sand be used for septic repairs.
The Pottle Street sand was not washed sand. The Town of Kingston
was invoiced for almost $1,700 in sand purchases by Lyons in
January and February of this year. Lyons told the Observer that a
portion of that sand was excavated from the town owned land on
Pottle Street. Highway specs for road sand also calls for it to be
washed. Again, the Pottle Street material is not washed, there
being no washing facility on site.
A view of the Pottle
Street acreage clearly delineates the area which has been
excavated. Lying adjacent to the railroad right of way, the area
is rich with sand deposits. The ability to screen the material on
site adds greatly to the value of the aggregate. The same
excavator that pulls the sand from the ground is the same
machinery that loads it into the screener. The same equipment is
then able to fully load the rigs.
Overseers of the
ball field project have said that volunteer contractors like
Lyons, are utilized to excavate worthless materials and bring the
site to grade in accordance with engineering plans. Committee
member Gary Langenbach was visibly agitated when he told the
Observer that nobody was interested in the Pottle Field material
because it had no value. He named local businessman John Hamilton
as someone in the business who had no interest in the material.
When the Observer contacted Hamilton, he said he never spoke with
Langenbach or anyone else relative to the earth material. He
couldn’t understand why his name would be used as a reference
and was disturbed by what he observed after viewing the site. It
must be noted that the engineering plans call for any excess earth
material to be stockpiled at the town highway facility for future
municipal use.
Heath Norrie of
Plympton Sand & Gravel did tell the Observer that they were
contacted last Summer and asked if the excess material was of any
interest to them. After an inspection of the site, Norrie said
they declined because the product was spread out throughout the
site and contained too much silt for their purposes. He said they
were contacted by Peter Opachinski who is the Committee’s newest
member, having been appointed this past October. Members of the
Committee point out that Opachinski donated hundreds of thousands
of dollars in in-kind services in site work, topsoil screening and
other assignments. Additionally, he was paid $17,146.50 for land
clearing, chipping and hay bale installation.
Several problems
emerge: First, the Lyons material is not worthless. We contacted
several licensed engineers who reviewed plans and another who
inspected the site. We were told that all material in the industry
has value. There is a value to sand, gravel, tailings, rock and
clay. Specifically, we were advised that the material being worked
by Lyons had value which was substantially increased by on-site
processing. In fact, the material was of such quality it could
pass as washed sand.
Secondly, the work
being done does not conform to the plans or accepted practice. The
suspended Lyons mining activity undercuts the elevation grades.
Harvested materials were replaced with less desirable subsoil not
in conformance with the standard compaction process of layering
fill in 6-8" lifts, required by the engineering plans.
Industry experts advise us that problems will arise with fields
built upon non compacted fill. Earth settles over a course of time
and the resulting low spots require constant maintenance. At least
one field may be so affected. Gale Associates Engineer Andy
Fairbanks defended the practice by telling the Observer that no
ballfield is to be built over the non-compacted fill despite
engineering plans to the contrary. Fairbanks said if compaction is
required, it can be done later. The statement is ludicrous. While
errors certainly can be corrected, you don’t deliberately
introduce them into the process for "correction" and
additional costs at a later date. Gale Associates is the
contracting engineer for the project.
Thirdly, little
exists in writing. Detailed record keeping has been problematic
with the project’s overseers. In light of recent developments,
Town Counsel, through Town Administrator Kevin Donovan, has
requested a written statement enumerating understanding,
agreements and contracts relative to the ballfield. An examination
of the committee’s minutes provides no explanation or mention of
the Lyon’s involvement. The Observer attended the February 25th
committee meeting, where members attempted to explain that Lyons
was on site in order to determine the size of a large boulder
interfering with the project. No doubt the rock has caused
problems. Sizing an obstacle however, does not explain mining,
filling, processing and on site customer service.
As of press time the
screening unit has been removed from the site and the excavator
was pulled almost a week later. We still don’t know the terms
and conditions that allowed Billy Lyons to conduct commercial
operations on town owned land. It would be unfortunate if this
incident places in question the role of genuine contributors who
may indeed have reduced the collective cost of the ballfield
initiative. Delays caused by a stop work order are unfortunate.
The anthem driving the ballfield plan is "It’s about the
kids". Yes it is about the kids — but how we get to the
kids is about us. The kids are the destination at the end of a
long journey — short cuts around basic management principles and
sound business judgment — serve neither the kids nor the town.

Overview of the Pottle Street
Ballfields construction project. Area of unauthorized mining
is marked by the black & red box. Click on image to take a
virtual tour of the site.
________________
TKO
Community Forum
Today's Question: What
should be done about the Pottle Street Ballfield mess?  |